In August of 2017, Norex carried out a bespoke railing and gates contract at a river side apartment block in Leeds. This was part of the larger, multimillion flood alleviation scheme. The work itself consisted of matching existing railings to the exact specification. Working to tight deadlines, we were under pressure to supply and install within four weeks of instruction. This was a demanding challenge but one we managed to complete on time. More recently, we were able to carry out work to the walk bridge across the river Aire. This involved fixing custom made panels to the underside of the bridge parallel to the apartment block.

Works summary:

40 metres of 2 metre high bespoke, finial top railing.

1 No. double leaf vehicle swing gate to match.

2 No. single leaf pedestrian swing gates to match.

4 No. custom made ‘anti climb’ panels fixed to the underside of the walk bridge.